- Freeze dimensions from reliable finished references before production.
- Approve foundations, anchors and building interfaces before installation day.
- Confirm power, drainage, access, unloading and protected storage.
- Use one readiness sign-off with named responsible parties.
- Do not hide unresolved conditions behind a general ready status.
Best for
- Contractors preparing for delivery
- Dealers coordinating client sites
- Homeowners managing local trades
- Commercial project managers signing off readiness
Key information
Key specifications
- Dimensions
- Verified references, levels, diagonals and clearances
- Structure
- Approved foundations, anchors and attachment interfaces
- Services
- Power, controls and drainage routes prepared from actual documents
- Logistics
- Delivery route, unloading, storage and installation access confirmed
Available options
- Freestanding or wall-connected installation
- Single or multi-module assembly
- Preplanned ZIP screens and lighting
- Phased delivery for constrained sites
Quick comparison
| Status | Meaning | Action |
|---|---|---|
| Ready | Evidence complete and interfaces approved | Release delivery or installation |
| Conditional | Minor item open with owner and due date | Track before affected work |
| Not ready | Dimension, structure, service or access unresolved | Hold shipment or installation decision |
| Changed | Site differs from approved information | Re-survey and review drawings |
Reconcile the site with the approved drawing
Walk the installation area with the latest approved plan and elevation. Check overall width, projection, diagonals, post centers, finished heights, door swings, roof overhangs, walls and nearby equipment. Record deviations rather than asking installers to absorb them on site.
Final dimensions should reference stable construction. If paving, cladding, parapets or walls changed after measurement, decide whether the production drawing remains valid. Custom aluminum profiles cannot always be shortened or moved without affecting drainage, connections, finishes or warranty responsibilities.
- Latest drawing revision available on site
- Corner and post references physically identifiable
- Finished floor and threshold levels checked
- Doors, shutters and service panels clear
- Changes photographed and issued for review
Approve foundations, anchors and interfaces
Each post needs a verified route from the pergola frame through the base and anchors into suitable structure. Pavers, tiles, decking and screed are finishes unless a designed support below them has been confirmed. Wall connections require the same discipline: identify the receiving structure, waterproofing and flashing responsibility.
Do not drill until hidden services, reinforcement, edges and movement joints are understood. The local responsible party should approve foundation and anchoring details against the actual project inputs. Manufacturer drawings support coordination but do not replace local structural approval.
| Interface | Evidence before installation | Hold point |
|---|---|---|
| Post base | Location, level and supporting construction | No unverified finish-only fixing |
| Anchors | Approved type, embedment and edge conditions | No substitution without review |
| Wall connection | Structure, flashing and waterproofing detail | No sealant-only assumption |
| Hidden services | Scan, drawings or confirmed safe zones | No blind drilling |
Prepare drainage and electrical services
Mark every pergola drainage post and the final discharge route. Confirm that base details, finished levels and local drains do not conflict. Keep outlets away from doors and primary circulation, and retain access for cleaning and testing.
Build the electrical plan from the equipment actually ordered: roof motors, screens, lights, sensors and controllers. A qualified local trade should provide the correct supply, protection, isolation and outdoor cable routing. Do not assume a generic voltage or place cables inside drainage paths without an approved detail.
- Drainage posts and outlet directions marked
- Site drain or surface discharge accepted
- Equipment schedule issued to electrician
- Cable routes avoid moving parts and drill zones
- Isolation and controller access retained
Confirm delivery, unloading and storage
Compare package dimensions and handling requirements with gates, roads, lifts, stairs, corridors and turning points. Arrange suitable unloading equipment and trained personnel. Identify who receives the shipment, checks seals and package labels, and records visible damage before opening.
Store components dry, secure and supported according to the package instructions. Separate items by module or installation sequence without removing labels. Protect finished aluminum, motors, fabrics and glass from site traffic, cement dust, standing water and incompatible materials.
| Logistics item | Confirm before dispatch | Arrival record |
|---|---|---|
| Vehicle access | Route, booking and unloading area | Vehicle and seal photos |
| Handling | Equipment, personnel and package limits | Visible package condition |
| Storage | Dry, secure and protected zone | Package location by label |
| Sequence | Install order and module IDs | Shortage or damage report |
Use a written readiness sign-off
Hold a short pre-installation review with the site manager, installer and relevant trades. Mark each item ready, conditional or not ready. Every conditional item needs an owner and date. If a critical dimension, foundation, power route or access condition is unresolved, do not disguise it with a general statement that the site is ready.
The final handover pack should include approved drawings, component information, control assignments, test records, photographs, operating guidance and maintenance responsibilities. Good preparation reduces improvisation; it does not remove the need for competent installation and commissioning.
- Site and drawing match confirmed
- Structural and waterproofing approvals available
- Power and drainage prepared
- Delivery and storage booked
- Installer tools and access arranged
- Open items assigned with deadlines
- Commissioning and handover plan agreed
Project visuals
See the details in context


Common questions
When should site readiness be checked?+
Review it before production release, again before shipment and finally before installation starts.
Can approximate measurements be used?+
They can support budgeting, but production requires verified dimensions and stable references.
Can posts be fixed through paving?+
Only when the load path through the finish to suitable structure is approved and drainage or waterproofing is resolved.
Who supplies the electrical connection?+
The written project scope should assign it; a qualified local trade normally designs and installs the supply from actual equipment data.
What if the site changed after production?+
Record the difference and obtain technical review before modifying components or foundations.
Should the shipment arrive before foundations are finished?+
Only when protected storage and a coordinated program make that appropriate; otherwise delivery may create handling and damage risks.
About LUCY
Aluminum pergola systems for project buyers.
LUCY manufactures configurable aluminum pergola systems for residential, hospitality and commercial projects.
Project configuration review
Discuss your pergola project with LUCY.
Share the site location, dimensions, intended use and any available drawings. LUCY will review the relevant system, model and project interfaces.
Get a quote